Home Zone Final Consultation |
||||||||||||||||||||||||||||||||||||||||||
|
Transport
and Highways Department
London
Borough of Lambeth Blue
Star House 234
-244 Stockwell Road London
SW9 9SP |
|
29 July 2003
Dear Resident
RE:
Holmewood Home Zone Consultation meeting feedback
Thank
you to those residents who attended the meeting at Friends Meeting House on the
22nd of July. I hope you would agree that the meeting generated some
useful outcomes and we can now see the way forward to the delivery of the
Traffic Management Phase of the Homezone project.
This letter is to inform
all residents of what happened at the meeting as well as set out the plan for
getting the Traffic Management changes in place and Homezone works underway.
The traffic management
measures as set out in the letter and plans (dated 10 July 2003), namely the
Point of No Entry at the junction of Brixton Hill and Holmewood Road, and the
emergency access only gate which blocks through traffic along Holmewood Road
near the junction with Holmewood Gardens, were accepted in principal. It was
anticipated that these changes would have a positive effect in cutting traffic
flow and stopping 'rat-running' through the area.
However, concerns were
raised over the design, placement and effect of proposed traffic calming works
(raised tables, pinch points) on parking capacity in particular, and it was
agreed that more work needed to be done to come to a design solution most
suitable to all. To this end a decision was made to split the project into two
stages as below:
1)
The Point
no Entry at Brixton Hill and Emergency Services Access gate blocking off
Holmewood Road, to be put in place early September -and:
2)
Traffic
calming measures -pinch points, raised tables, build-outs and changes to
parking etc. To be re-designed with help of residents by early September and delivered
in November.
We are all aware that the
Homezone project has taken some time to progress, this option is being pursued
in order to put the Point of No Entry and Gate in place as soon as possible,
whilst allowing time to make minor changes to the design of traffic calming
measures.
It
must be stressed that this is not a re-design of the whole scheme, and while
changes may be made to placement, size and design/materials used in the traffic
calming measures, the basic layout of the scheme will not differ greatly.
In order to speed up the
final consultation process for the traffic scheme, six representatives to cover
all areas of the Homezone have come forward to act as the contact point for
myself and the design team.
The names and contact
details of area representatives can be found attached to this letter. If you
have a particular concern or issue you would like to raise in relation to the
proposals, please contact the person allocated to your area before the 6th
of September 2003.
The area representative
will then meet with myself and the design team to pass on information gathered,
and assist us to make whatever changes are possible within budget, design and
technical limits. Once the plans have been amended and agreed upon, they will
be sent back to the designers and traffic engineers for completion.
The new outline project
timeline is now as follows
22
July 2003 - Residents
meeting took place -way forward for design and implementation agreed.
July 2003 - Traffic Management Order for Point No Entry and
closing off Holmewood Road (Stage 1) started -this is the first legal
requirement for traffic 'bylaw' that allows us to do the work.
August
2003 -
Resurfacing of Holmewood Gardens.
August
2003 -
Area representatives to gather information on residents concerns and issues
with current plans.
September
2003 -
Point of No Entry and gate closing off Holmewood Road to through traffic put in
place.
September
2003 -
Design team to meet with area representatives to discuss issues and make amendments
to plans for traffic calming proposals. Changes incorporated into scheme, final
plans produced by designer and engineers.
October
2003 - Traffic
Management Order for stage 2 submitted and advertised (6 weeks).
November
2003 -
On-site construction of amended scheme begins.
December
2003 -Traffic
Management Scheme completed.
I look forward to
continuing to work with you to complete this stage of the Homezone project . If
you have any questions or would like to discuss anything in this letter please
do not hesitate to contact me at the details below. Thank you.
Yours faithfully
Cameron
Martyn
Special
Projects Officer
Lambeth
Council
Direct
Line: 020 7926 0186
Lambeth
Transport
Transportation
& Highways Group
3rd
Floor, Blue Star House
234-244
Stockwell Road
London
SW9 9SP
Telephone
02079262124
Facsimile
02079262357
Please identify the area
representative closest to your address and pass on any concerns or issues you
may have with the current plans (dated 10 July 2003) before 5th September 2003.
Brixton Hill Point No
Entry
Robin Russell-Pavier - 3
Holmewood Road - ph 020 8671 8735
Holmewood
Road/Holmewood Gardens Junction
Duncan
Law - 46 Holmewood Road - ph 020 8678 6617
Junction
at Northern End Holmewood Gardens
Sarah
Thorley - 23 Holmewood Gardens- ph 020 8674 5447
Holmewood
Gardens East
Sarah
Prynn - 61 Holmewood Gardens - ph 07785 503803
Maplestead
Road
Peter
Robinson - 10 Maplestead Road - ph 020 8674 7171
Cotherstone
Road
Dene
Ledwidge - 4 Cotherstone Road - ph 07956 419573